May 28, 2009

Updated photo but little progress



New pictures of CP2 phase 1 show some progress between 13 April 2009 and 18 April 2009. 5 Floors to be exact. At this rate, to complete the structure work of towers 7,8 and 9, it'll take 5 more months, taking it to Oct 2009. Thereafter, the internal and external work will start. If you see the previous photos, there has been no progress in the external work of towers 1 to 6 in the last 6 months. So it can be safely concluded that phase 1 will not be ready anytime before March 2010.



Belgravia progress seems to have slowed down. While there is some progress in all towers, the rate is dismal . Lets keep track of it and see how it progresses

No comments:

Post a Comment